Republic of the Philippines
SAN PABLO CITY WATER DISTRICT
Maharlika Highway, Brgy. San Gabriel, San Pablo City
Telefax. No. (049) 503-0075
Invitation to Bid
Contract No. 2025-226
Installation of the following: a) 75mm.Ø Small Distribution Pipelines at Purok 3, Brgy. San Miguel, San Pablo City; b) 75mm.Ø Small
Distribution Pipelines at Brgy. Santisimo Rosario, San
Pablo City; and c) 50mm.Ø Small Distribution
Pipelines at Brgy. San Rafael, (Near Laurel
Ville Subdivision) San Pablo City
1. The San Pablo City Water District, through the 2025 Approved Budget intends to apply the sum of One Million Six Hundred Ninety-Five Thousand Two Hundred Eighteen and 84/100 Pesos (Php 1,695,218.84) only being the Approved Budget for the Contract (ABC) to payments under the contract for Contract No. 2025-226 Installation of the following: a) 75mm.Ø Small Distribution Pipelines at Purok 3, Brgy. San Miguel, San Pablo City; b) 75mm.Ø Small Distribution Pipelines at Brgy. Santisimo Rosario, San Pablo City; and c) 50mm.Ø Small Distribution Pipelines at Brgy. San Rafael, (Near Laurel Ville Subdivision) San Pablo City. Bids received in excess of the ABC shall be automatically rejected at bid opening.
2. The San Pablo City Water District now invites bids for the above Procurement Project. Completion of the Works is required within Forty-Five (45) Working Days upon approval. Bidders should have completed a contract similar to the Project. The description of an eligible bidder is contained in the Bidding Documents, particularly, in Section II (Instructions to Bidders).
3. Bidding will be conducted through open competitive bidding procedures using non-discretionary “pass/fail” criterion as specified in the 2016 revised Implementing Rules and Regulations (IRR) of Republic Act (RA) No. 9184.
4. Interested bidders may obtain further information from San Pablo City Water District and inspect the Bidding Documents at the address given below from 8:00 o’clock in the morning up to 5:00 o’clock in the afternoon.
5. A complete set of Bidding Documents may be acquired by interested bidders on December 1, 2025 to December 21, 2025 from the given address below and upon payment of the applicable fee for the Bidding Documents, pursuant to the latest Guidelines issued by the GPPB, in the amount of Five Thousand Pesos (Php 5,000.00) only. The Procuring Entity shall allow the bidder to present its proof of payment for the fees by presenting the Official Receipt personally at the given address below.
6. The San Pablo City Water District will hold a Pre-Bid Conference on December 9, 2025 at 1:00 o’clock in the afternoon at San Pablo City Water District Regional Training Center, Maharlika Highway, Brgy. San Gabriel, San Pablo City, which shall be open to prospective bidders.
7. Bids must be duly received by the BAC Secretariat through manual submission at the office address as indicated below on or before December 21, 2025 at 2:00 o’clock in the afternoon. Late bids shall not be accepted.
8. All bids must be accompanied by a bid security in any of the acceptable forms and in the amount stated in ITB Clause 16.
9. Bid opening shall be on December 21, 2025 at 2:00 o’clock in the afternoon at the given address below. Bids will be opened in the presence of the bidders’ representatives who choose to attend the activity.
10. In case the due date falls on a non-working day, i.e. Saturday and Sunday, legal holiday, or special non-working holiday, the deadline shall be moved on the next working day.
11. The San Pablo City Water District reserves the right to reject any and all bids, declare a failure of bidding, or not award the contract at any time prior to contract award in accordance with Sections 35.6 and 41 of the 2016 revised Implementing Rules and Regulations (IRR) of RA No. 9184, without thereby incurring any liability to the affected bidder or bidders.
12. For further information, please refer to:
ROXAINE LOURREST A. CARANDANG
Head, BAC Secretariat
San Pablo City Water District
Maharlika Highway, Brgy. San Gabriel,
San Pablo City 4000, Laguna, Philippines
bac@spcwd.org.ph
Tel No:
Laguna Trunkline: (049) 562-9955 loc. 124 or 125 or 128
Manila Line: (02) 8396-9550 loc. 124 or 125 or 128
Direct Line: (049) 503-0075
Approved by:
EFREN R. DELA PAZ
Chairman, Bids and Awards Committee
Noted by:
MILDRED C. MORGA
Acting General Manager
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Checklist of Technical and Financial Documents
I. TECHNICAL COMPONENT ENVELOPE
Class “A” Documents
Legal Documents
?
(a) Valid PhilGEPS Registration Certificate (Platinum Membership) (all pages) in accordance with Section 8.5.2 of the IRR;
Technical Documents
?
(b) Statement of the prospective bidder of all its ongoing government and private contracts, including contracts awarded but not yet started, if any, whether similar or not similar in nature and complexity to the contract to be bid; and
?
(c) Statement of the bidder’s Single Largest Completed Contract (SLCC) similar to the contract to be bid, except under conditions provided under the rules; and
?
(d) Special PCAB License in case of Joint Ventures and registration for the type and cost of the contract to be bid; and
?
(e) Original copy of Bid Security. If in the form of a Surety Bond, submit also a certification issued by the Insurance Commission or original copy of Notarized Bid Securing Declaration; and
(f) Project Requirements, which shall include the following:
?
a. Organizational chart for the contract to be bid;
?
b. List of contractor’s key personnel (e.g., Project Manager, Project Engineers, Materials Engineers, and Foremen), to be assigned to the contract to be bid, with their complete qualification and experience data;
?
c. List of contractor’s major equipment units, which are owned, leased, and/or under purchase agreements, supported by proof of ownership or certification of availability of equipment from the equipment lessor/vendor for the duration of the project, as the case may be; and
?
(g) Original duly signed Omnibus Sworn Statement (OSS) and if applicable, Original Notarized Secretary’s Certificate in case of a corporation, partnership, or cooperative; or Original Special Power of Attorney of all members of the joint venture giving full power and authority to its officer to sign the OSS and do acts to represent the Bidder.
Financial Documents
?
(h) The prospective bidder’s computation of Net Financial Contracting Capacity (NFCC).
Class “B” Documents
?
(i) If applicable, duly signed joint venture agreement (JVA) in accordance with RA No. 4566 and its IRR in case the joint venture is already in existence or
duly notarized statements from all the potential joint venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful.
II. FINANCIAL COMPONENT ENVELOPE
?
(j) Original of duly signed and accomplished Financial Bid Form; and
Other documentary requirements under RA No. 9184
?
(k) Original of duly signed Bid Prices in the Bill of Quantities; and
?
(l) Duly accomplished Detailed Estimates Form, including a summary sheet indicating the unit prices of construction materials, labor rates, and equipment rentals used in coming up with the Bid; and
?
(m) Cash Flow by Quarter.
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
SAN PABLO CITY WATER DISTRICT
San Pablo City
WORK ORDER
W.O. No.
Project Classification: Date
DISTRIBUTION LINES
Title:
PROPOSED INSTALLATION OF 75MM Ø SMALL DISRIBUTION PIPELINES AT
PUROK 3, BRGY. SAN MIGUEL, SAN PABLO CITY
Description of Work Location of Work
Proposed installation of 75mm Ø PVC Pipelines with Purok 3 , Brgy. San Miguel
an estimated length of 810.70 LM. San Pablo City
Starting Date : Upon approval
Schedule Completion: 20 working days
Date Completed:
Final Completion:
Justification Work Breakdown
1 Excavation / Concrete demolition
As per Extension of Service Distribution Line 2 Pipelaying/Boring Works
3 Interconnection
4 Concrete Thrust Blocking.
5 Backfilling.
6 Restoration
7 Flushing and Disinfection.
8 Clean-up.
Sketch of Work to be done Project Cost
Particulars:
Materials P610,065.00
See Attached Plan Labor P228,000.00
Overhead Cost P94,852.69
Total Project Cost.: P932,917.69
Manner of undertaking the project Action taken by the General Manager
By Administration Approved Reason for disapproval/deferred:
By Contractor Disapproved
Joint Deferred
Prepared by: Checked by: Reviewed and Recommended
for Approval by:
ENGR. HAZEL S. GERONIMO ARCH. MARIO A. BONDAD ENGR. LAZARO FERDINAN S. ABRIGO
Acting Division Manager A, EWRD Division Manager A, ED Department Manager A, TSD
Reviewed and Recommended Budget checked by: Pre-Audited by:
for Approval by:
ENGR. ALVIN A. SANTIAGO ROMMEL B. DE LUNA RAUL F. CASTAÑEDA
Acting Department Manager A, OD Division Manager A , T and B Supervising Internal Control Officer
Approved by:
ENGR. ELEUTERIO D. AMANTE
General Manager
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
SAN PABLO CITY WATER DISTRICT
San Pablo City
WORK ORDER
W.O. No.
Project Classification: Date
DISTRIBUTION LINES
Title:
PROPOSED INSTALLATION OF 75MM Ø SMALL DISRIBUTION PIPELINES AT
BRGY. SANTISIMO ROSARIO , SAN PABLO CITY
Description of Work Location of Work
Proposed installation of 75mm Ø PVC Pipelines with Brgy. Santisimo Rosario
an estimated length of 321.8 LM. San Pablo City
Starting Date : Upon approval
Schedule Completion: 12 working days
Date Completed:
Final Completion:
Justification Work Breakdown
1 Excavation / Concrete demolition
As per Extension of Service Distribution Line 2 Pipelaying/Boring Works
3 Interconnection
4 Concrete Thrust Blocking.
5 Backfilling.
6 Restoration
7 Flushing and Disinfection.
8 Clean-up.
Sketch of Work to be done Project Cost
Particulars:
Materials P322,460.00
See Attached Plan Labor P98,400.00
Overhead Cost P60,210.96
Total Project Cost.: P481,070.96
Manner of undertaking the project Action taken by the General Manager
By Administration Approved Reason for disapproval/deferred:
By Contractor Disapproved
Joint Deferred
Prepared by: Checked by: Reviewed and Recommended
for Approval by:
ENGR. HAZEL S. GERONIMO ARCH. MARIO A. BONDAD ENGR. LAZARO FERDINAN S. ABRIGO
Acting Division Manager A, EWRD Division Manager A, ED Department Manager A, TSD
Reviewed and Recommended Budget checked by: Pre-Audited by:
for Approval by:
ENGR. ALVIN A. SANTIAGO ROMMEL B. DE LUNA RAUL F. CASTAÑEDA
Acting Department Manager A, OD Division Manager A , T and B Supervising Internal Control Officer
Approved by:
ENGR. ELEUTERIO D. AMANTE
General Manager
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
SAN PABLO CITY WATER DISTRICT
San Pablo City
WORK ORDER
W.O. No.
Date
Project Classification:
DISTRIBUTION LINES
Title:
PROPOSED INSTALLATION OF 50 MM Ø SMALL DISTRIBUTION PIPELINES AT
SAN RAFAEL ( NEAR LAUREL VILLE SUBDIVISION ) , SAN PABLO CITY
Description of Work Location of Work
Proposed installation of 50mm Ø Small distribution line Brgy. San Rafael
with an estimated length of 246 LM. San Pablo City
Starting Date : Upon approval
Schedule Completion: 18 working days
Date Completed:
Final Completion:
Justification Work Breakdown
1 Concrete Demolition
As per Extension of Service Distribution Line 2 Trench Excavation
3 Pipelaying with backfilling
4 Interconnection point
5 Installation of FITTINGS/FH/BOV
6 Thrustblock
7 Disinfection and Flushing
8 Restoration.
9 Clean-up
Sketch of Work to be done Project Cost
Particulars:
Materials P123,515.00
See Attached Plan Labor P108,000.00
Overhead Cost P49,715.19
Total Project Cost.: P281,230.19
Manner of undertaking the project Action taken by the General Manager
By Administration Approved Reason for disapproval/deferred:
By Contractor Disapproved
Joint Deferred
Prepared by: Checked by: Reviewed and Recommended
for Approval by:
ENGR. HAZEL S. GERONIMO ARCH. MARIO A. BONDAD ENGR. LAZARO FERDINAN S. ABRIGO
Acting Division Manager A, EWRD Division Manager A, ED Department Manager A, TSD
Reviewed and Recommended Budget checked by: Pre-Audited by:
for Approval by:
ENGR. ALVIN A. SANTIAGO ROMMEL B. DE LUNA RAUL F. CASTAÑEDA
Acting Department Manager A, OD Division Manager A , T and B Supervising Internal Control Officer
Approved by:
ENGR. ELEUTERIO D. AMANTE
General Manager
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
San Pablo City Water District
San Pablo City
PROPOSED INSTALLATION OF 75MM Ø SMALL DISRIBUTION PIPELINES AT PUROK 3, BRGY. SAN MIGUEL, SAN PABLO CITY
WORK SCHEDULE
No. ACTIVITIES Days
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 Excavation / Concrete demolition
2 Pipelaying /Boring
3 Interconnection Interconnection Works
4 Concrete Thrust Blocking.
5 Backfilling
6 Restoration
7 Flushing and Disinfection
8 Clean-Up
Prepared by: Checked by: Reviewed and Recommended for Approval by:
ENGR. HAZEL S. GERONIMO ARCH. MARIO A. BONDAD ENGR. LAZARO FERDINAN S. ABRIGO ENGR. ALVIN A. SANTIAGO
Acting Division Manager A, EWRD Division Manager A, ED Department Managr A, TSD Acting Department Manager A, OD
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
San Pablo City Water District
San Pablo City
PROPOSED INSTALLATION OF 75MM Ø SMALL DISRIBUTION PIPELINES AT BRGY. SANTISIMO ROSARIO , SAN PABLO CITY
WORK SCHEDULE
No. ACTIVITIES Days
1 2 3 4 5 6 7 8 9 10 11 12
1 Excavation / Concrete demolition
2 Pipelaying /Boring
3 Interconnection Interconnection Works
4 Concrete Thrust Blocking.
5 Backfilling
6 Restoration
`
7 Flushing and Disinfection
ROXAINE LOURREST A. CARANDANG
Head, BAC Secretariat
San Pablo City Water District